Caltrain Reduces Service for Two Weeks to Expedite Electrification Construction

From Monday, December 5, through Sunday, December 18, Caltrain will temporarily reduce its service levels to accommodate Electrification construction. On weekdays, the service will be reduced to 68 trains per day down from the current 104 trains per day, including the suspension of Baby Bullet service.

Weekend train service on December 10 and 11, and December 17 and 18, 2022, will be replaced by bus service between Belmont and Mountain View. Riders can transfer to SamTrans bus service through the affected area, which will increase travel time for riders by 60-90 minutes. The weekend bus bridges will serve all regular weekend stops between Belmont and Mountain View stations with timed train connections on both ends.

During this period of construction, train service will also end early on weeknights and weekends to accelerate work being performed on the entire railroad. The last northbound train each evening will depart Tamien Station at 9:01 p.m. and the last southbound train will depart San Francisco Station at 9:22 p.m.Ā 

This construction work includes signal cutover work at 16 grade crossings, requiring a 24/7 single-tracking window between Belmont and Mountain View.Ā Ā 

The December temporary schedule is available here. For shuttle service, please refer to www.caltrain.com/shuttles. Riders are encouraged to look at other available transit options during this period of construction.Ā 

On Monday, December 19, Caltrain will revert to the regular weekday and weekend schedule.Ā  Ā 

Caltrainā€™s historic Electrification project is the first undertaking in North America in a generation in which diesel trains and their infrastructure components are transitioned to an electrified system. The project will improve the customer experience by increasing the number of trains, modernizing service and adding new safety elements. The new trains will feature onboard displays with digital trip information, increased storage capacities, more power outlets and spacious bathrooms with a baby-changing table. Electrification will also help meet ambitious regional and state climate action goals by lowering greenhouse gas emissions, improving air quality and relieving traffic congestion. Additionally, electrified service will advance equity along the corridor by reducing noise and air pollution while increasing access for priority equity neighbors. It will also set the framework for Californiaā€™s future High Speed Rail network.Ā 

###

About Caltrain: Owned and operated by the Peninsula Corridor Joint Powers Board, Caltrain provides rail service from San Francisco to San Jose, with commute service to Gilroy. Serving the region since 1863, Caltrain is the oldest continually operating rail system west of the Mississippi. Looking to the future, Caltrain is set to electrify the corridor by 2024, which will reduce diesel emissions and add more service to more stations while advancing the agencyā€™s equity goals.

Follow Caltrain on Facebook and Twitter.

Free translation assistance is available. Para traducciĆ³n llama al 1.800.660.4287; 如需ēæ»č­Æ,č«‹é›» 1.800.660.4287.

Media Contact: Dan Lieberman, 650.622.2492