Bridge Rehabilitation Projects - Overview
Project Lead:
Caltrain
Project Limits:
Rail bridges along the corridor through
San Francisco, San Mateo and Santa Clara
counties (See Individual Projects for more details)
Construction Cost:
$115 million (estimated)
Begin Construction:
2005 – The first bridge project began in Oct. 2005
End Construction:
2010 – The various bridge projects will be
completed at different times, with the final
project scheduled for completion in this year.
Reason for Project:
This project is necessary to upgrade bridges,
which have deteriorated with time and regular use.
Scope of Work:
Each bridge has specific requirements, however,
a general review of the scope of work that will be
done during this project includes:
- Replacing whole existing bridges
- Replacing bridge decks
- Reinforcing bridges to meet seismic standards