Construction, Installation and Maintenance: May 6 to May 12, 2017

 NOTICE


Construction, Installation and Maintenance: May 6
to May 12, 2017


 


Please note, information reported below is subject
to change without notice. If you are a member of the media, please call
650.508.7927 to confirm any information below. For all other inquiries, please
call the Construction Outreach Hotline at 650.508.7726.


 


Rail Grinding Work


On April 26, Caltrain will began a three-week rail grinding
project that will result in measurably reduced noise for neighbors next to the
right of way and a safer, smoother ride for passengers. A rail-mounted,
industrial-size grinder will be used to smooth out defects and restore the
shape of the rail. 


The rail grinding equipment must be
used at between 10 p.m. and 4:30 a.m. when there is limited or no train
service. The work will begin in San Francisco and proceed south to the cities
of South San Francisco, San Bruno, Burlingame, San Mateo and San Jose. Work at
any one location will be completed in one or two nights. The entire project is
expected to be complete by May 19.


During the rail maintenance, there
will be noise impacts to areas immediately adjacent to the rail alignment while
the grinding is taking place. We apologize for the inconvenience.


Construction


 


San Francisco
Roadway Bridges Project


Night/Weekend
Work
There is
night and weekend work scheduled for Friday, May 5 through Monday, May 8 at the
22nd Street location. Crews will perform pipe repair work.


Weekday
Work


* In
general, all weekday construction activity will occur between 7 a.m. and 5 p.m.
on Monday through Friday. Neighbors may experience construction noise during
this time. We apologize for the inconvenience.


22nd
Street Bridge
Monday, May
8 to Friday, May 12, crews will install fencing on the north barrier rail and
will continue utility work in the area.  


Pedestrian
access will be switched to the southern sidewalk while crews perform work on
the north portion of the bridge.


The closure of 22nd Street between Iowa Street and Pennsylvania
began on Tuesday, April 19, 2016.
During the closure, vehicular access
to 22nd Street between Iowa Street and Pennsylvania Avenue will
remain closed during the removal and replacement of the bridge. Detour
signage will be in place to direct vehicular and pedestrian traffic during the
closure.


San Carlos Transit Center Project


Night/Weekend Work


There is no night
or work scheduled at the San Carlos Transit Center Project.


 


Weekday Work


Monday, May 8 to Friday, May 12, crews will continue parking lot improvements.
Neighbors may experience construction noise and traffic during this time. We
apologize for the inconvenience. El Camino Real traffic may also be reduced to
one lane during construction activities.


Some parking spaces in the Caltrain parking
lot and along the eastside of El Camino between Cherry and Arroyo have been permanently
removed as part of the project. Caltrain customers are encouraged to park at
the Belmont Caltrain Station during construction.


Background
The San Carlos
Multi-Modal Transit Center Project (Transit Center) is located on the west side
of the railroad corridor at the site of the existing San Carlos Caltrain
Station. The Transit Center project consists of transforming the existing San
Carlos Caltrain Station parking lot into a multi-modal transit center that will
better serve the community by improving safety and accessibility between
SamTrans fixed route bus services, Caltrain commuter rail services, local
shuttles, pedestrians and bicyclists. For more information on the project,
please visit
www.samtrans.com/sctc.


The Transit Center project is part of the
larger mixed-use transit-oriented development, the San Carlos Transit Village,
which is a joint development between SamTrans and Prometheus Real Estate
Group.  For information about the San
Carlos Transit Village Project visit: 
http://cityofsancarlos.org/planning/projects/san_carlos_transit_village/default.asp


Los Gatos
Creek Bridge Replacement Project Weekly Update


 


Night/Weekend Work
As part of the Los Gatos Creek
Bridge Project, there is night work scheduled from Friday, May 5 to Friday, May
12. Crews are also scheduled to work on Saturday, May 13 and Sunday, May 14.
Crews will be installing sheet and cast-in-drilled-hole piles within the
Caltrain right-of-way. To limit the impact to railroad operations, these
activities must be conducted at night or on the weekend when there is limited
or no train service.


 


Additional night work will be required throughout the project.


 


During the night and weekend work, neighbors will hear
additional noises from heavy machinery and from equipment backup alarms. In
addition, generators will be used for night time activities to power portable
light towers. Caltrain will implement noise mitigation measures for residents
directly adjacent to the project site. We apologize for any inconvenience these
activities may cause.


Weekday
Work
Monday, May
8 to Friday, May 12, crews will continue installation of the retaining wall
structure and will mobilize drilling equipment for the tail track abutment.


Background
Caltrain,
in cooperation with the City of San Jose, is preparing to replace the railroad
bridge crossing at Los Gatos Creek in San Jose. The current bridge was
built in 1935, and in order to maintain safe rail operations and meet current
seismic safety standards, the bridge must be replaced. The project will also
include installation of a tail track south of the San Jose Diridon station. The
tail track will provide improved operations at the station and minimize
system-wide delays. Construction is expected to be complete in early 2018.


In order to maintain regular train service, some
activities will be conducted during nights and weekends, outside of normal
train service hours. Neighbors may experience construction noise and light
during these times. We apologize for any inconvenience this may cause.
For more information on the Los
Gatos Creek Bridge Replacement Project, please visit www.caltrain.com/losgatos.
For questions about the project, please call the Caltrain Construction
Hotline at 650.508.7726 or email lgcbridge@caltrain.com.


Peninsula Corridor Electrification Project


The
Peninsula Corridor Electrification Project (PCEP) is a key component of the
Caltrain Modernization program. The PCEP would electrify the Caltrain Corridor
from San Francisco’s 4th and King Caltrain Station to approximately the Tamien
Caltrain
Station.


 


The primary purpose
of the Project is to improve Caltrain system performance, reduce long-term
environmental impact by reducing noise, improving regional air quality and
reducing greenhouse gas emissions. An electrified Caltrain system would better
address Peninsula commuters’ vision of increased service and improved
travel times in an environmentally friendly and reliable way. This
also is expected to help accommodate increase system ridership through improved
system operations. 


 


San Francisco


No work
anticipated.


 


Brisbane


No work
anticipated.


 


South San Francisco


No work
anticipated.


 


San Bruno


No work
anticipated.


 


Millbrae


May 8 to
May 12, Caltrain will be doing work during the day to remove project materials.
We apologize for any inconvenience this may cause. The field team will work as
quietly as possible.


 


Burlingame


May 8 to
May 12, Caltrain will be doing work during the day to remove project materials.
We apologize for any inconvenience this may cause. The field team will work as
quietly as possible.


 


San Mateo


May 8 to
May 13, Caltrain will be doing work during the day and night, from 7:00 p.m. to
6:00 a.m., to survey and locate underground utilities and remove project
materials. We apologize for any inconvenience this may cause. The field team
will work as quietly as possible.


 


During
night work hours at San Mateo, Hayward Park and Hillsdale stations,
all passengers will board and
de-board from the same platform. Please look for the signs to indicate which
platform to use. If you have any questions, feel free to call the project
hotline at 650-399-9659 or toll-free at 855-463-4373.


 


Belmont


No work
anticipated.


 


San Carlos


No work
anticipated.


 


Redwood City


No work
anticipated.


 


Unincorporated San
Mateo County


No work
anticipated.


 


Atherton


No work
anticipated.


 


Menlo Park


No work
anticipated.


 


Palo Alto


No work
anticipated.


 


Mountain View


No work
anticipated.


 


Sunnyvale


No work
anticipated.


 


Santa
Clara


No work
anticipated.


 


San Jose


May 8 to
May 12, Caltrain will be doing work during the day to survey and locate
underground utilities. We apologize for any inconvenience this may cause. The
field team will work as quietly as possible.


 


For more information, please call the dedicated outreach line at
650.508.6499; visit the website at
www.caltrain.com/PCEP or email calmod@caltrain.com.


Maintenance

Caltrain will perform routine maintenance at several locations next week. To
avoid disruptions to service, the work will mainly take place Saturday through
Friday from 8 p.m. to 6 a.m. For more information about this type of work,
click
here,
or call 650.508.7726.


San Francisco to San Jose


Saturday, May 6, to Friday, May 12, crews will
pressure wash and perform janitorial work at Caltrain stations between the San
Francisco and Tamien stations.


 


Monday, May 8, to Friday, May 12, crews will weld
and grind rail at various locations between the San Francisco and Tamien
stations. The welding crew uses air compressors, gas-powered generators, small
power tools, electric-arc welders and propane heaters. Neighbors may experience
construction noise during this time. Crews will work as quietly as possible.


 


Brisbane to South San Francisco


Monday, May 8, to Friday, May 12, crews will
resurface rail between the Brisbane and South San Francisco stations.
Resurfacing corrects the alignment of uneven rails to make them smooth,
minimizing the jerks and bumps experienced by passengers and reducing the
mechanical strain on the rails. Neighbors may experience construction noise
during this time. Crews will work as quietly as possible.


 


Mountain View to Sunnyvale


Monday, May 8, to Friday, May 12, crews will
replace ties between the San Antonio and Sunnyvale stations. Caltrain uses
several different on-track, self-propelled machines to replace cross ties, and
neighbors may experience construction noise during this time. Crews will work
as quietly as possible.