Construction, Installation and Maintenance: January 21 to January 27, 2017

 NOTICE


 


Construction, Installation and Maintenance: January 21 to January 27,
2017


 


Please note, information reported below is subject to change without
notice. If you are a member of the media, please call 650.508.7927 to confirm
any information below. For all other inquiries, please call the Construction
Outreach Hotline at 650.508.7726.


 


Construction


 


San Francisco Roadway Bridges Project



Night/Weekend Work


Work scheduled for
January 19 to January 23 has been delayed due to weather.

There is night and weekend work planned for Thursday, January 26 to Monday,
January 30. Crews will be installing the precast bridge girders. Work may be
delayed depending on weather conditions. 


 


Access to
residential driveways on 22nd Street between Pennsylvania Avenue and
Iowa Street may be temporarily impacted from 12 a.m. to 8 a.m. Thursday,
January 26 to Monday, January 30. Crews will be delivering and unloading
precast bridge girders during these times. Delivery of the girders may block
access to driveways along 22nd Street for up to 15 minutes at a
time. Access will not be blocked unnecessarily. Crews will be on site and will
restore access as soon as possible.


 


Weekday Work


* In general, all weekday
construction activity will occur between 7 a.m. and 5 p.m. on Monday through
Friday. Neighbors may experience construction noise during this time. We
apologize for the inconvenience.


 


22nd
Street Bridge


Monday, January 23 to Friday,
January 27, crews will prepare for the installation of the precast bridge
girders.


 


The closure of 22nd Street
between Iowa Street and Pennsylvania began on Tuesday, April 19, 2016.
During the closure, vehicular access
to 22nd Street between Iowa Street and Pennsylvania Avenue will
remain closed during the removal and replacement of the bridge. Detour
signage will be in place to direct vehicular and pedestrian traffic during the
closure.


A temporary pedestrian bridge has been
installed to maintain limited pedestrian access across 22nd Street.
The temporary pedestrian bridge is intended for use by Caltrain customers
accessing the 22nd Street Caltrain Station.


San Carlos Transit Center Project
Night/Weekend Work


There is night and weekend work
planned for Monday, January 23 to Friday, January 27.
Crews will
begin work on the sidewalk, curb and gutter along El Camino Real. Neighbors may
experience construction noise during this time. We apologize for the
inconvenience. El Camino Real traffic may be reduced to one lane during
construction activities.


Weekday Work


Monday,
January 23, to Friday, January 27, crews will continue improvements to the
south Caltrain parking lot. Crews will continue utility work and will begin
work on the sidewalk, curb and gutter along El Camino Real. 


Some parking
spaces in the Caltrain parking lot and along the eastside of El Camino between
Cherry and Arroyo will be removed permanently as part of the project. On-site
notices will be provided at least 72 hours in advance before the removal of
parking.


Background
The San Carlos Multi-Modal Transit Center Project (Transit Center) is
located on the west side of the railroad corridor at the site of the existing
San Carlos Caltrain Station. The Transit Center project consists of
transforming the existing San Carlos Caltrain Station parking lot into a
multi-modal transit center that will better serve the community by improving
safety and accessibility between SamTrans fixed route bus services, Caltrain
commuter rail services, local shuttles, pedestrians and bicyclists. For more
information on the project, please visit
www.samtrans.com/sctc.


The
Transit Center project is part of the larger mixed-use transit-oriented
development, the San Carlos Transit Village, which is a joint development
between SamTrans and Prometheus Real Estate Group.  For information about the San Carlos Transit
Village Project visit: 
http://cityofsancarlos.org/planning/projects/san_carlos_transit_village/default.asp


Los Gatos Creek
Bridge Pre-Construction Utility Work


Night/Weekend Work


There is no night or weekend work scheduled for
the project at this time.


Weekday Work


There is currently no work scheduled at the
Los Gatos Creek Bridge site.


For more information on the Los Gatos Creek
Bridge Replacement Project, please visit
www.caltrain.com/losgatos.
Construction for the bridge replacement is expected to begin in Early 2016.


Peninsula
Corridor Electrification Project


The Peninsula Corridor
Electrification Project (PCEP) is a key component of the Caltrain Modernization
program. The PCEP would electrify the Caltrain Corridor from San Francisco’s
4th and King Caltrain Station to approximately the Tamien Caltrain Station.


 


The primary purpose of
the Project is to improve Caltrain system performance, reduce long-term
environmental impact by reducing noise, improving regional air quality and
reducing greenhouse gas emissions. An electrified Caltrain system would better
address Peninsula commuters’ vision of increased service and improved
travel times in an environmentally friendly and reliable way. This
also is expected to help accommodate increase system ridership through improved
system operations.
 


 


San Francisco


January 23 to January 27,
Caltrain will be doing work during the day to survey and locate underground utilities.
We apologize for any inconvenience this may cause and the field team will work
as quietly as possible.


 


Brisbane


January 23 to January 27,
Caltrain will be doing work during the day to survey and locate underground utilities.
We apologize for any inconvenience this may cause and the field team will work
as quietly as possible.


 


South San Francisco


January
23 to January 28, Caltrain will be doing work during the day to confirm soil
conditions, survey and locate underground utilities. We apologize for any
inconvenience this may cause and the field team will work as quietly as
possible.


 


San Bruno


January
23 to January 28, Caltrain will be doing work during the day to confirm soil
conditions, survey and locate underground utilities. We apologize for any
inconvenience this may cause and the field team will work as quietly as
possible.


 


Millbrae


January
23 to January 28, Caltrain will be doing day and night work to confirm soil
conditions, survey and locate underground utilities. We apologize for any
inconvenience this may cause and the field team will work as quietly as
possible.


 


Burlingame


January
23 to January 28, Caltrain will be doing day and night work to confirm soil
conditions, survey and locate underground utilities. We apologize for any
inconvenience this may cause and the field team will work as quietly as
possible.


 


San Mateo


January
23 to January 28, Caltrain will be doing day and night work to confirm soil
conditions, survey and locate underground utilities. We apologize for any
inconvenience this may cause and the field team will work as quietly as
possible.


 


Belmont


January
25 and 26, Caltrain will be doing work overnight to confirm soil conditions,
survey and locate underground utilities. We apologize for any inconvenience
this may cause and the field team will work as quietly as possible.


 


San Carlos


January
25 and 26, Caltrain will be doing work overnight to confirm soil conditions,
survey and locate underground utilities. We apologize for any inconvenience
this may cause and the field team will work as quietly as possible.


         


Redwood City


January
25 and 26, Caltrain will be doing work overnight to confirm soil conditions,
survey and locate underground utilities. We apologize for any inconvenience
this may cause and the field team will work as quietly as possible.


 


Unincorporated San Mateo County


January
23 to January 28, Caltrain will be doing work overnight to confirm soil
conditions, survey and locate underground utilities. We apologize for any
inconvenience this may cause and the field team will work as quietly as
possible.


 


Atherton


January
25 and 26, Caltrain will be doing work overnight to confirm soil conditions,
survey and locate underground utilities. We apologize for any inconvenience
this may cause and the field team will work as quietly as possible.


 


Menlo Park


January
23 to January 28, Caltrain will be doing work during the day and night to
confirm soil conditions, survey and locate underground utilities. We apologize
for any inconvenience this may cause and the field team will work as quietly as
possible.


 


Palo Alto


January
23 to January 28, Caltrain will be doing work during the day and night to
confirm soil conditions, survey and locate underground utilities. We apologize
for any inconvenience this may cause and the field team will work as quietly as
possible.


 


Mountain View


January
23 to January 28, Caltrain will be doing work during the day and night to
confirm soil conditions, survey and locate underground utilities. We apologize
for any inconvenience this may cause and the field team will work as quietly as
possible.


 


At
San Antonio station, on January 23 a single track schedule may be in place
during nighttime work hours, 6:00 p.m. to 6:00 a.m.


 


Sunnyvale


January
23 to January 28, Caltrain will be doing work during the day and night to
confirm soil conditions, survey and locate underground utilities. We apologize
for any inconvenience this may cause and the field team will work as quietly as
possible.


 


Santa Clara


No work anticipated.


 


San Jose


No work anticipated.


 


 


For more
information, please call the dedicated outreach line at 650.508.6499; visit the
website at
www.caltrain.com/PCEP or email calmod@caltrain.com.


Installation


Communications
Based Overlay Signal System (CBOSS) Positive Train Control (PTC) Project


The CBOSS
PTC Project is an advanced signal system that will equip the corridor and
trains with federally-mandated safety technology and will increase system
capacity to help accommodate future ridership demand.


The
project will monitor and, if necessary, control train movement in the event of
human error. This will increase safety by:


  • Eliminating
    the risk of train-to-train collisions.
  • Reducing
    risk of potential derailments by enforcing speed limits.
  • Providing
    additional safety for railroad workers on the tracks.


 


  • Improving
    grade crossing performance to reduce gate downtime and improve local
    traffic circulation.


 


The CBOSS PTC Project
is also a key component of the Caltrain Modernization Program, which will
electrify the Caltrain Corridor by 2020. An electrified Caltrain will be
cleaner and quieter and will upgrade the system to provide faster and/or more
frequent service to more stations and riders.




To implement the project, Caltrain will be identifying utilities, digging a
small trench and/or boring close to the tracks to install fiber optic cable. In
order to maintain daytime train service, Caltrain will be performing some of
this work at night.


San Francisco


On
January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests
on the corridor as part of the final phase of implementing the Advanced Signal
System Project. To test the Advanced Signal System, including the roadway
crossings, a test train will run through the corridor between 9:00 p.m. and
7:00 a.m. Tests are conducted at night to avoid disruption of most of regular
train service and properly record the results. Neighbors may experience
standard gate crossing noise and horns during this time and we apologize for
any inconvenience this may cause.


 


Brisbane


On
January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests
on the corridor as part of the final phase of implementing the Advanced Signal
System Project. To test the Advanced Signal System, including the roadway
crossings, a test train will run through the corridor between 9:00 p.m. and
7:00 a.m. Tests are conducted at night to avoid disruption of most of regular
train service and properly record the results. Neighbors may experience
standard gate crossing noise and horns during this time and we apologize for
any inconvenience this may cause.


 


South San Francisco


On
January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests
on the corridor as part of the final phase of implementing the Advanced Signal
System Project. To test the Advanced Signal System, including the roadway
crossings, a test train will run through the corridor between 9:00 p.m. and
7:00 a.m. Tests are conducted at night to avoid disruption of most of regular
train service and properly record the results. Neighbors may experience
standard gate crossing noise and horns during this time and we apologize for
any inconvenience this may cause.


 


San Bruno


On
January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests
on the corridor as part of the final phase of implementing the Advanced Signal
System Project. To test the Advanced Signal System, including the roadway
crossings, a test train will run through the corridor between 9:00 p.m. and
7:00 a.m. Tests are conducted at night to avoid disruption of most of regular
train service and properly record the results. Neighbors may experience
standard gate crossing noise and horns during this time and we apologize for
any inconvenience this may cause.


 


Millbrae


On
January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests
on the corridor as part of the final phase of implementing the Advanced Signal
System Project. To test the Advanced Signal System, including the roadway
crossings, a test train will run through the corridor between 9:00 p.m. and
7:00 a.m. Tests are conducted at night to avoid disruption of most of regular
train service and properly record the results. Neighbors may experience
standard gate crossing noise and horns during this time and we apologize for
any inconvenience this may cause.


 


Burlingame


On
January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests
on the corridor as part of the final phase of implementing the Advanced Signal
System Project. To test the Advanced Signal System, including the roadway
crossings, a test train will run through the corridor between 9:00 p.m. and
7:00 a.m. Tests are conducted at night to avoid disruption of most of regular
train service and properly record the results. Neighbors may experience
standard gate crossing noise and horns during this time and we apologize for
any inconvenience this may cause.


 


San Mateo


On
January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests
on the corridor as part of the final phase of implementing the Advanced Signal
System Project. To test the Advanced Signal System, including the roadway
crossings, a test train will run through the corridor between 9:00 p.m. and
7:00 a.m. Tests are conducted at night to avoid disruption of most of regular
train service and properly record the results. Neighbors may experience
standard gate crossing noise and horns during this time and we apologize for
any inconvenience this may cause.


 


Belmont


On
January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests
on the corridor as part of the final phase of implementing the Advanced Signal
System Project. To test the Advanced Signal System, including the roadway
crossings, a test train will run through the corridor between 9:00 p.m. and
7:00 a.m. Tests are conducted at night to avoid disruption of most of regular
train service and properly record the results. Neighbors may experience
standard gate crossing noise and horns during this time and we apologize for
any inconvenience this may cause.


 


San Carlos


On
January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests
on the corridor as part of the final phase of implementing the Advanced Signal
System Project. To test the Advanced Signal System, including the roadway
crossings, a test train will run through the corridor between 9:00 p.m. and
7:00 a.m. Tests are conducted at night to avoid disruption of most of regular
train service and properly record the results. Neighbors may experience
standard gate crossing noise and horns during this time and we apologize for
any inconvenience this may cause.


 


Redwood City


On
January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests
on the corridor as part of the final phase of implementing the Advanced Signal
System Project. To test the Advanced Signal System, including the roadway
crossings, a test train will run through the corridor between 9:00 p.m. and
7:00 a.m. Tests are conducted at night to avoid disruption of most of regular
train service and properly record the results. Neighbors may experience
standard gate crossing noise and horns during this time and we apologize for
any inconvenience this may cause.


 


Unincorporated San Mateo County


On
January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests
on the corridor as part of the final phase of implementing the Advanced Signal
System Project. To test the Advanced Signal System, including the roadway
crossings, a test train will run through the corridor between 9:00 p.m. and
7:00 a.m. Tests are conducted at night to avoid disruption of most of regular
train service and properly record the results. Neighbors may experience
standard gate crossing noise and horns during this time and we apologize for
any inconvenience this may cause.


 


Atherton


On
January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests
on the corridor as part of the final phase of implementing the Advanced Signal
System Project. To test the Advanced Signal System, including the roadway
crossings, a test train will run through the corridor between 9:00 p.m. and
7:00 a.m. Tests are conducted at night to avoid disruption of most of regular
train service and properly record the results. Neighbors may experience
standard gate crossing noise and horns during this time and we apologize for
any inconvenience this may cause.


 


Menlo Park


On
January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests
on the corridor as part of the final phase of implementing the Advanced Signal
System Project. To test the Advanced Signal System, including the roadway
crossings, a test train will run through the corridor between 9:00 p.m. and
7:00 a.m. Tests are conducted at night to avoid disruption of most of regular
train service and properly record the results. Neighbors may experience
standard gate crossing noise and horns during this time and we apologize for any
inconvenience this may cause.


 


Palo Alto


On
January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests
on the corridor as part of the final phase of implementing the Advanced Signal
System Project. To test the Advanced Signal System, including the roadway
crossings, a test train will run through the corridor between 9:00 p.m. and
7:00 a.m. Tests are conducted at night to avoid disruption of most of regular
train service and properly record the results. Neighbors may experience standard
gate crossing noise and horns during this time and we apologize for any
inconvenience this may cause.


 


Mountain View


On
January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests
on the corridor as part of the final phase of implementing the Advanced Signal
System Project. To test the Advanced Signal System, including the roadway
crossings, a test train will run through the corridor between 9:00 p.m. and
7:00 a.m. Tests are conducted at night to avoid disruption of most of regular
train service and properly record the results. Neighbors may experience
standard gate crossing noise and horns during this time and we apologize for
any inconvenience this may cause.


 


Sunnyvale


On
January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests
on the corridor as part of the final phase of implementing the Advanced Signal
System Project. To test the Advanced Signal System, including the roadway
crossings, a test train will run through the corridor between 9:00 p.m. and
7:00 a.m. Tests are conducted at night to avoid disruption of most of regular
train service and properly record the results. Neighbors may experience
standard gate crossing noise and horns during this time and we apologize for
any inconvenience this may cause.


 


Santa Clara


On
January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests
on the corridor as part of the final phase of implementing the Advanced Signal
System Project. To test the Advanced Signal System, including the roadway
crossings, a test train will run through the corridor between 9:00 p.m. and
7:00 a.m. Tests are conducted at night to avoid disruption of most of regular
train service and properly record the results. Neighbors may experience
standard gate crossing noise and horns during this time and we apologize for
any inconvenience this may cause.


 


San Jose


On
January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests
on the corridor as part of the final phase of implementing the Advanced Signal
System Project. To test the Advanced Signal System, including the roadway
crossings, a test train will run through the corridor between 9:00 p.m. and
7:00 a.m. Tests are conducted at night to avoid disruption of most of regular
train service and properly record the results. Neighbors may experience
standard gate crossing noise and horns during this time and we apologize for
any inconvenience this may cause.


 


For more
information, please call the dedicated outreach line at 650.508.6499; visit the
website at
www.caltrain.com/CBOSSPTC or email caltrainptc@samtrans.com.


Maintenance

Caltrain will perform routine maintenance at several locations next week. To
avoid disruptions to service, the work will mainly take place Saturday through
Friday from 8 p.m. to 6 a.m. For more information about this type of work,
click
here,
or call 650.508.7726.


San Francisco to
San Jose


Saturday,
January 21, to Friday, January 27, crews will pressure wash and perform
janitorial work at Caltrain stations between the San Francisco and Tamien
stations.


 


South San Francisco to Burlingame


Monday, January 23,
to Friday, January 27, crews will resurface rail between the South San
Francisco and Broadway stations. Resurfacing corrects the alignment of uneven
rails to make them smooth, minimizing the jerks and bumps experienced by
passengers and reducing the mechanical strain on the rails. Neighbors may
experience construction noise during this time. Crews will work as quietly as
possible.


 


Millbrae to Belmont


Monday, January 23
to Friday, January 27, crews will replace ties between the Millbrae and Belmont
stations. Caltrain uses several different on-track, self-propelled machines to
replace cross ties, and neighbors may experience construction noise during this
time. Crews will work as quietly as possible


 


San Jose


Monday, January
23 to Friday, January 27, crews will weld and grind rail near the San Jose
Diridon Station. The welding crew uses air compressors, gas-powered generators,
small power tools, electric-arc welders and propane heaters. Neighbors may
experience construction noise during this time. Crews will work as quietly as
possible.