Construction, Installation and Maintenance: February 4 to February 10, 2017

 NOTICE


 


Construction, Installation and Maintenance: February 4 to February 10,
2017


 


Please note, information reported below is subject to change without
notice. If you are a member of the media, please call 650.508.7927 to confirm
any information below. For all other inquiries, please call the Construction
Outreach Hotline at 650.508.7726.


 


Construction


 


San Francisco Roadway Bridges Project


 


Night/Weekend
Work


There is no night or weekend work
scheduled for the San Francisco Roadway Bridges Project.


Weekday
Work


* In
general, all weekday construction activity will occur between 7 a.m. and 5 p.m.
on Monday through Friday. Neighbors may experience construction noise during
this time. We apologize for the inconvenience.


 22nd
Street Bridge
Monday,
February 6 to Friday, February 10, crews install utility supports
and deck formwork.


The closure of 22nd Street
between Iowa Street and Pennsylvania began on Tuesday, April 19, 2016.
During the closure, vehicular access
to 22nd Street between Iowa Street and Pennsylvania Avenue will
remain closed during the removal and replacement of the bridge. Detour
signage will be in place to direct vehicular and pedestrian traffic during the
closure.


A temporary pedestrian bridge has been
installed to maintain limited pedestrian access across 22nd Street.
The temporary pedestrian bridge is intended for use by Caltrain customers
accessing the 22nd Street Caltrain Station.


San Carlos Transit Center Project
Night/Weekend Work


There is no night or weekend work currently
scheduled at the San Carlos Transit Center Project.


Weekday Work


Monday, February
6, to Friday, February 10, crews will continue work on the sidewalk, curb and
gutter along El Camino Real. Neighbors may experience construction noise during
this time. We apologize for the inconvenience. El Camino Real traffic may also
be reduced to one lane during construction activities.


Some parking
spaces in the Caltrain parking lot and along the eastside of El Camino between
Cherry and Arroyo will be removed permanently as part of the project. On-site
notices will be provided at least 72 hours in advance before the removal of
parking. Caltrain customers are encouraged to park at the Belmont Caltrain
Station during construction.


Background
The San Carlos Multi-Modal Transit Center Project (Transit Center) is
located on the west side of the railroad corridor at the site of the existing
San Carlos Caltrain Station. The Transit Center project consists of
transforming the existing San Carlos Caltrain Station parking lot into a
multi-modal transit center that will better serve the community by improving
safety and accessibility between SamTrans fixed route bus services, Caltrain
commuter rail services, local shuttles, pedestrians and bicyclists. For more
information on the project, please visit www.samtrans.com/sctc.


The
Transit Center project is part of the larger mixed-use transit-oriented
development, the San Carlos Transit Village, which is a joint development
between SamTrans and Prometheus Real Estate Group.  For information about the San Carlos Transit
Village Project visit: 
http://cityofsancarlos.org/planning/projects/san_carlos_transit_village/default.asp


Los Gatos Creek
Bridge Pre-Construction Utility Work


Night/Weekend Work


There is no night or weekend work scheduled for
the project at this time.


Weekday Work


Monday, February 6 to Friday, February 10,
crews will install netting beneath the Los Gatos Creek Bridge and will remove
fencing in the area. Construction activities are expected to start February 13,
2017.


For more information on the Los Gatos Creek
Bridge Replacement Project, please visit
www.caltrain.com/losgatos.
Construction for the bridge replacement is expected to begin in mid- February.


Installation


San Francisco
On February 4; February 6 – 8; and February 10, Caltrain
will be conducting safety tests on the corridor as part of the final phase of
implementing the Advanced Signal System Project. To test the Advanced Signal
System, including the roadway crossings, a test train will run through the
corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid
disruption of most of regular train service and properly record the results.
Neighbors may experience standard gate crossing noise and horns during this
time and we apologize for any inconvenience this may cause.


Brisbane 
On February 4; February 6 – 8; and February 10, Caltrain
will be conducting safety tests on the corridor as part of the final phase of
implementing the Advanced Signal System Project. To test the Advanced Signal
System, including the roadway crossings, a test train will run through the
corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid
disruption of most of regular train service and properly record the results.
Neighbors may experience standard gate crossing noise and horns during this
time and we apologize for any inconvenience this may cause.


South San Francisco 
On February 4; February 6 – 8; and February 10, Caltrain
will be conducting safety tests on the corridor as part of the final phase of
implementing the Advanced Signal System Project. To test the Advanced Signal
System, including the roadway crossings, a test train will run through the
corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid
disruption of most of regular train service and properly record the results.
Neighbors may experience standard gate crossing noise and horns during this
time and we apologize for any inconvenience this may cause.


San Bruno 
On February 4; February 6 – 8; and February 10, Caltrain
will be conducting safety tests on the corridor as part of the final phase of
implementing the Advanced Signal System Project. To test the Advanced Signal
System, including the roadway crossings, a test train will run through the
corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid
disruption of most of regular train service and properly record the results.
Neighbors may experience standard gate crossing noise and horns during this
time and we apologize for any inconvenience this may cause.


Millbrae 
On February 4; February 6 – 8; and February 10, Caltrain
will be conducting safety tests on the corridor as part of the final phase of
implementing the Advanced Signal System Project. To test the Advanced Signal
System, including the roadway crossings, a test train will run through the
corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid
disruption of most of regular train service and properly record the results.
Neighbors may experience standard gate crossing noise and horns during this
time and we apologize for any inconvenience this may cause.


Burlingame 
On February 4; February 6 – 8; and February 10, Caltrain
will be conducting safety tests on the corridor as part of the final phase of
implementing the Advanced Signal System Project. To test the Advanced Signal
System, including the roadway crossings, a test train will run through the
corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid
disruption of most of regular train service and properly record the results.
Neighbors may experience standard gate crossing noise and horns during this time
and we apologize for any inconvenience this may cause.


San Mateo 
On February 4; February 6 – 8; and February 10, Caltrain
will be conducting safety tests on the corridor as part of the final phase of
implementing the Advanced Signal System Project. To test the Advanced Signal
System, including the roadway crossings, a test train will run through the
corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid
disruption of most of regular train service and properly record the results. Neighbors
may experience standard gate crossing noise and horns during this time and we
apologize for any inconvenience this may cause.


Belmont
On February 4; February 6 – 8; and February 10,Caltrain will
be conducting safety tests on the corridor as part of the final phase of
implementing the Advanced Signal System Project. To test the Advanced Signal
System, including the roadway crossings, a test train will run through the
corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid
disruption of most of regular train service and properly record the results.
Neighbors may experience standard gate crossing noise and horns during this
time and we apologize for any inconvenience this may cause.


San Carlos 
On February 4; February 6 – 8; and February 10, Caltrain
will be conducting safety tests on the corridor as part of the final phase of
implementing the Advanced Signal System Project. To test the Advanced Signal
System, including the roadway crossings, a test train will run through the corridor
between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid
disruption of most of regular train service and properly record the results.
Neighbors may experience standard gate crossing noise and horns during this
time and we apologize for any inconvenience this may cause.


Redwood City 
On February 4; February 6 – 8; and February 10, Caltrain
will be conducting safety tests on the corridor as part of the final phase of
implementing the Advanced Signal System Project. To test the Advanced Signal
System, including the roadway crossings, a test train will run through the
corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid
disruption of most of regular train service and properly record the results.
Neighbors may experience standard gate crossing noise and horns during this
time and we apologize for any inconvenience this may cause.


Unincorporated San Mateo
County 
On February 4; February 6 – 8; and February 10, Caltrain
will be conducting safety tests on the corridor as part of the final phase of
implementing the Advanced Signal System Project. To test the Advanced Signal
System, including the roadway crossings, a test train will run through the
corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption
of most of regular train service and properly record the results. Neighbors may
experience standard gate crossing noise and horns during this time and we
apologize for any inconvenience this may cause.


Atherton 
On February 4; February 6 – 8; and February 10, Caltrain
will be conducting safety tests on the corridor as part of the final phase of
implementing the Advanced Signal System Project. To test the Advanced Signal
System, including the roadway crossings, a test train will run through the corridor
between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid
disruption of most of regular train service and properly record the results.
Neighbors may experience standard gate crossing noise and horns during this
time and we apologize for any inconvenience this may cause.


Menlo Park 
On February 4; February 6 – 8; and February 10, Caltrain
will be conducting safety tests on the corridor as part of the final phase of
implementing the Advanced Signal System Project. To test the Advanced Signal
System, including the roadway crossings, a test train will run through the
corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid
disruption of most of regular train service and properly record the results.
Neighbors may experience standard gate crossing noise and horns during this
time and we apologize for any inconvenience this may cause.


Palo Alto
On February 4; February 6 – 8; and February 10, Caltrain
will be conducting safety tests on the corridor as part of the final phase of
implementing the Advanced Signal System Project. To test the Advanced Signal
System, including the roadway crossings, a test train will run through the
corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid
disruption of most of regular train service and properly record the results.
Neighbors may experience standard gate crossing noise and horns during this
time and we apologize for any inconvenience this may cause.


Mountain View 
On February 4; February 6 – 8; and February 10, Caltrain
will be conducting safety tests on the corridor as part of the final phase of
implementing the Advanced Signal System Project. To test the Advanced Signal
System, including the roadway crossings, a test train will run through the
corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid
disruption of most of regular train service and properly record the results.
Neighbors may experience standard gate crossing noise and horns during this
time and we apologize for any inconvenience this may cause.


Sunnyvale
On February 4; February 6 – 8; and February 10, Caltrain
will be conducting safety tests on the corridor as part of the final phase of
implementing the Advanced Signal System Project. To test the Advanced Signal
System, including the roadway crossings, a test train will run through the
corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid
disruption of most of regular train service and properly record the results.
Neighbors may experience standard gate crossing noise and horns during this
time and we apologize for any inconvenience this may cause.


Santa Clara
On February 4; February 6 – 8; and February 10, Caltrain
will be conducting safety tests on the corridor as part of the final phase of
implementing the Advanced Signal System Project. To test the Advanced Signal
System, including the roadway crossings, a test train will run through the
corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid
disruption of most of regular train service and properly record the results.
Neighbors may experience standard gate crossing noise and horns during this
time and we apologize for any inconvenience this may cause.


San Jose
On February 4; February 6 – 8; and February 10, Caltrain
will be conducting safety tests on the corridor as part of the final phase of
implementing the Advanced Signal System Project. To test the Advanced Signal
System, including the roadway crossings, a test train will run through the
corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid
disruption of most of regular train service and properly record the results.
Neighbors may experience standard gate crossing noise and horns during this
time and we apologize for any inconvenience this may cause.


Maintenance


Caltrain will perform routine maintenance at several locations next week. To
avoid disruptions to service, the work will mainly take place Saturday through
Friday from 8 p.m. to 6 a.m. For more information about this type of work,
click
here,
or call 650.508.7726.


San Francisco to
San Jose


Saturday, February
4, to Friday, February 10, crews will pressure wash and perform janitorial work
at Caltrain stations between the San Francisco and Tamien stations.


 


Monday, February
6, to Friday, February 10, crews will weld and grind rail at various locations
between the San Francisco and Tamien stations. The welding crew uses air
compressors, gas-powered generators, small power tools, electric-arc welders
and propane heaters. Neighbors may experience construction noise during this
time. Crews will work as quietly as possible.


 


South San Francisco to Burlingame


Monday, February
6, to Friday, February 10, crews will resurface rail between the South San
Francisco and Broadway stations. Resurfacing corrects the alignment of uneven
rails to make them smooth, minimizing the jerks and bumps experienced by
passengers and reducing the mechanical strain on the rails. Neighbors may
experience construction noise during this time. Crews will work as quietly as
possible.


 


San Bruno to Millbrae


Monday, February
6, to Friday, February 10, crews will replace ties between the San Bruno and Millbrae
stations. Caltrain uses several different on-track, self-propelled machines to
replace cross ties, and neighbors may experience construction noise during this
time. Crews will work as quietly as possible


 


San Jose


Monday, February
6, to Friday, February 10, crews will weld and grind rail near the San Jose
Diridon Station. The welding crew uses air compressors, gas-powered generators,
small power tools, electric-arc welders and propane heaters. Neighbors may
experience construction noise during this time. Crews will work as quietly as
possible.