Weekly Construction, Installation and Maintenance Notice

Sign Up for Email Updates

Construction, Installation and Maintenance

Construction is advancing along the Caltrain corridor! To accommodate the brand new electric trains, construction crews will begin work in the four San Francisco tunnels starting in October. Crews will create additional clearance in the tunnel sides to accommodate the new trains and will install anchor bolts in the tunnel ceilings to facilitate the installation of the overhead contact system that will power the new electric trains. For more information visit CalMod.org/SFtunnels.

In order to facilitate work in the tunnels, trains will not operate on weekends between San Francisco and Bayshore Stations from October 6, 2018 to late Spring 2019. Caltrain service will stop at Bayshore Station and a bus bridge will transport passengers to the 22nd and 4th & King Stations. Weekday service will not be impacted. For more service information visit www.Caltrain.com/SFweekendClosure.
Please note, information reported below is subject to change without notice. If you are a member of the media, please call 650.508.7927 to confirm any information below. For all other inquiries, please call the Construction Outreach Hotline at 650.508.7726. 
  

South San Francisco Station Improvement Project

Night/Weekend Work

No night work planned.

Weekday Work

 

 

Monday, October 22, to Friday, October 26, crews will continue street work on Poletti Way between East Grand Avenue and Corporate Drive. Crews will also continue installing pole foundations within the Station Area.

 

Neighbors may hear additional noises from heavy machinery and equipment backup alarms. We apologize for any inconvenience these activities may occur.

 

Traffic Notices

 

Poletti Way Traffic Notice

Starting August 8, temporary lane closures of Poletti Way between East Grand Avenue and Corporate Drive will be required to facilitate the construction of street improvements being completed as part of the Caltrain South San Francisco Station Improvement Project. One lane of Poletti Way will remain accessible to local and through traffic during construction. Please pay attention to additional signage when using Poletti Way.

 

After the completion of the South San Francisco Station Project, Poletti Way will become a two-way street, with the Southbound lane being reserved for buses serving passengers at the new South San Francisco Station.

 

Linden Avenue Grade Crossing

 

Starting August 24, Caltrain will begin installation of overhead wire along the corridor in South San Francisco as part of Caltrain Electrification. Vehicles may experience short delays at the Linden Avenue grade crossing during wire installation. We apologize for any inconvenience this may cause. For more information on Caltrain Electrification, please visit www.calmod.org.

 

 

back to top

 

25th Avenue Grade Separation Project

PG&E Pipeline Relocation Work

 

PG&E is relocating a natural gas pipeline for the 25th Avenue Grade Separation Project. The project will improve safety and reduce local traffic congestion. On Saturday, October 3-, and then on Monday, October 22 to Friday, October 26, crews will continue to work from 7:30 a.m. to 5:30 p.m. Pacific Blvd., from S. Delaware to the Hillsdale Blvd. on-ramp, will continue to be closed 24 hours, 7 days a week until early November (see map here).

PG&E will clearly mark all work areas, and traffic flaggers will help to direct traffic. Please plan for minor delays and detours when driving through this area. Businesses on S. Delaware will be open as usual. If you have any questions please contact your local PG&E representative Butch Harris at 408.282.7517 or send an email to gasprojectinfo@pge.com.

 

Grade Separation Night/Weekend Work

 

 

On Saturday, October 20 from 7:00 a.m. to 5:00 p.m.:

  • Crews will conduct fiber optic relocation work in the Caltrain temporary parking lot between 31st Avenue and Curiosity
  • A lane will be closed on Pacific close to Antioch for crews to conduct fiber optic relocation work

 

 

Please note: PG&E will work on Saturday, October 13 during daytime hours (see above).  

 

Grade Separation Weekday Work

 

Traffic Information (Monday, October 22 to Friday, October 26)

  • E: 25th Avenue: Lane closure on the eastbound center lane between El Camino Real and S. Delaware from 7:00 a.m. to 5:00 p.m. Street parking may be limited and flaggers may be assisting with traffic coordination at the railroad crossing. All businesses along E. 25th Avenue will remain open during construction.
  • Pacific Blvd. (at Concar Dr.): Road closure due to fiber optic cable relocation. Pedestrian access will be maintained during the closure.
  • Pacific Blvd. (near Antioch): Lane closure from 7:00 a.m. to 5:00 p.m. Flaggers will assist bi-directional traffic flow.
  • Please see the 24/7 road closure on Pacific Blvd. (near Hillsdale on-ramp) above due to PG&E work.

 

 

Construction Work

Monday, October 22 to Friday, October 26, crews will work on:

  • The abutments and girders at the Pedestrian Underpass
  • A bent cap at 25th Avenue
  • Abutments at 28th Avenue
  • The MSE walls from Borel to 25th Avenue (trenching and installing the lower panels) and north of Borel (installing panels)

 

Also, on Friday, October 28, crews will conduct deck waterproofing work at the Borel Creek Bridge.

 

Parking Lot Impacts

On Monday, October 22 through December 2019, there will be no access to the Caltrain temporary parking lot from 31st Avenue. Vehicles can access the lot from 28th Avenue at S. Delaware. Please note some spaces in the temporary parking lot located on the eastside of the Hillsdale Station will be unavailable due to the construction work.

 

We apologize for any inconvenience while this important safety improvement project is being constructed.

Background

 

Caltrain, in cooperation with the City of San Mateo, will raise the tracks and slightly lower the road (grade separate) at E. 25th Avenue in San Mateo. This will improve safety for both motorists and pedestrians, and it will reduce local traffic congestion in San Mateo. In addition, the project will create new east-west street connections at 28th and 31st Avenues; and as part of the project improvements, Caltrain will build a new elevated Hillsdale Station with updated amenities at E. 28th Avenue. 

 

Construction is expected to be complete in early 2020. In order to maintain regular train service, some activities will be conducted during nights and weekends, outside of normal train service hours. Neighbors may experience construction noise and light during these times. We apologize for any inconvenience this may cause. 

 

For more information on the 25th Avenue Grade Separation Project, please visit www.caltrain.com/25thgs. For questions about the project, please call the Caltrain Construction Hotline at 650.508.7726 or email smgradesep@caltrain.com.

 

crossingimprovementsGrade Crossing Improvements Project

Night/Weekend Work

 

None.

Weekday Work

 

San Francisco

16th Street: As early as Friday, October 19, crews may be removing sidewalk.

 

Background

 

The Grade Crossing Improvements Project is a one-year project to improve the safety at 15 grade crossings (places where streets cross the tracks) along the corridor from San Francisco to San Jose. Improvements include more clearly-marked pedestrian crossings with new paint striping and lettering; tactile pavement markers; and guardrails. Medians will also be installed or improved at eight locations.

 

For more information please visit www.caltrain.com/GCimprovements. For questions about the project, please call the Caltrain Construction Hotline at 650.508.7726 or email construction@caltrain.com

 

 back to top

 

Positive Train Control (PTC) Project

Night/Weekend Work

 

Starting Wednesday, October 17 to Friday, October 19, Caltrain will conduct informal, low-impact testing at night from just south of De La Cruz Blvd. in Santa Clara to just south of Lewis Rd. in San Jose. Testing will occur from 10:00 p.m. to 4:00 a.m. The testing includes a high-rail vehicle (similar to a pick-up truck) moving slowly down the right of way to check the GPS coordinates of test signals, switches, signage, and stations. No horns will be used and gates will not be impacted.

 

Weekday Work

 

None.

Background

 

Caltrain is continuing work on its Positive Train Control (PTC) Project-an advanced signal system that will equip the corridor with federally-mandated technology that will improve safety and increase reliability and operating performance. For more information on the PTC project, please visit www.caltrain.com/PTC. For questions about the project, please call the Caltrain Construction Hotline at 650.508.7726 or email PTC@caltrain.com

 

SunnyvaleSunnyvale Station Rehabilitation Project

Night/Weekend Work

 

None. However, see platform impacts below.

Weekday Work

 

On Monday, October 15 to Friday, October 19, crews will be working. For passengers, please note:

  • The north pedestrian crossing will be closed due to construction. All passengers will need to use the south pedestrian crossing to access the platforms.
  • The south pedestrian crossing will remain open but may be blocked when a train arrives. Passengers are encouraged to arrive early to the station to allow enough time to cross the tracks to meet their train.

 

 

We apologize for any inconvenience the construction activities may cause. More rider information can be found at www.caltrain.com/stations/sunnyvalestation.

Background

 

The Sunnyvale Station Rehabilitation Project is a safety improvement project that will update the station's platform length to allow for a six car train to fit the platform. It will also relocate the pedestrian crossing at the northbound end of the station platform approximately 80 feet closer to Mathilda Avenue to prevent the crossing at the southbound end of the platform from being blocked. In addition, the project will replace uneven pavers on the platform with a smooth concrete surface.

Construction is expected to be complete in December. Neighbors may experience construction noise during these times. We apologize for any inconvenience this may cause. To sign up for weekly updates, visit www.Caltrain.com/SunnyvaleStation. For additional questions or concerns regarding this project, please call our dedicated Construction Outreach Line at 650.508.7726 or email construction@caltrain.com.

 

 

 back to top

pcepPeninsula Corridor Electrification Project

Peninsula Corridor Electrification Project

 

Caltrain Electrification is a key component of the Caltrain Modernization program which will electrify the Caltrain Corridor from San Francisco's 4th and King Caltrain Station to approximately the Tamien Caltrain Station.

 

The primary purpose of Caltrain Electrification is to improve Caltrain system performance, reduce long-term environmental impact by reducing noise, improving regional air quality and reducing greenhouse gas emissions. An electrified Caltrain system would better address Peninsula commuters' vision of increased service and improved travel times in an environmentally friendly and reliable way. This also is expected to help accommodate increase system ridership through improved system operations. 

 

For information on upcoming community construction update meetings, please visit the Caltrain Electrification Project events page at http://calmod.org/events/

San Francisco

 

On October 20, Caltrain will be working during the day to perform utility potholing at the 4th and King and 22nd Street station platforms. Day work hours will be from 7 a.m. to 7 p.m.

 

On October 20 through October 26, Caltrain will perform work in the four tunnels in San Francisco. Crews will perform grouting and drilling work in the tunnels as well as notching work to provide additional clearance for the new electric trains. Crews will also perform potholing work outside of the tunnels. Weekend tunnel work will be around the clock from Friday evening to Monday morning. Weekday work will be from 8 p.m. to 5 a.m. For more information on the tunnel work, visit www.calmod.org/SFTunnels. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

Brisbane

 

On October 20, Caltrain will be working during the day to perform utility potholing at the Bayshore Station platform. Day work hours will be from 7 a.m. to 7 p.m.

 

October 20 to October 26, Caltrain will be working during the day to install conduit. Day work hours will be from 7 a.m. to 7 p.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

 

During work hours at the Bayshore station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.

South San Francisco

 

October 20 through October 26, Caltrain will be working during the day to install conduit, and to install rebar and concrete at the Traction Power Substation Facility, and during the night to relocate signal cables and install equipment on poles. Day work hours will be from 7 a.m. to 7 p.m.Night work hours will be 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible. During construction motorists and pedestrians may experience intermittent delays while crews move equipment through at-grade crossings.

 

During work hours at the South San Francisco station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.

San Bruno

 

October 20 through October 26, Caltrain will be working during the day to install conduit, and during the night to relocate signal cables and install equipment on poles. Day work hours will be from 7 a.m. to 7 p.m.Night work hours will be 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible. During construction motorists and pedestrians may experience intermittent delays while crews move equipment through at-grade crossings.

 

During work hours at the San Bruno station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.

Millbrae

 

October 20 through October 26, Caltrain will be working during the day to locate underground utilities and install conduit, and during the night to relocate signal cables and to install equipment on poles. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible. During construction motorists and pedestrians may experience intermittent delays while crews move equipment through at-grade crossings.

 

During work hours at the Millbrae station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.

Burlingame

 

October 20 through October 26, Caltrain will be working during the day to locate underground utilities, and during the night to relocate signal cables. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible. During construction motorists and pedestrians may experience intermittent delays while crews move equipment through at-grade crossings.

 

During work hours at the Burlingame station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.

San Mateo

 

October 20 through October 26, Caltrain will be working during the day to locate underground utilities, and during the night to install foundations and relocate signal cables. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible. During construction motorists and pedestrians may experience intermittent delays while crews move equipment through at-grade crossings.

 

During work hours at the San Mateo station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.

Belmont

 

October 20 through October 26, Caltrain will be working during the day to locate underground utilities, and during the night to install foundations and relocate signal cables. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

 

During work hours at the Belmont station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.

San Carlos

 

October 20 through October 26, Caltrain will be working during the day to locate underground utilities, and during the night to install foundations and relocate signal cables. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

 

During work hours at the San Carlos station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.

Redwood City

 

October 20 through October 26, Caltrain will be working during the day to locate underground utilities, and during the night to install foundations and relocate signal cables. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible. During construction motorists and pedestrians may experience intermittent delays while crews move equipment through at-grade crossings.

 

During work hours at the Redwood City station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.

 

Unincorporated San Mateo County

 

October 20 through October 26, Caltrain will be working during the day to locate underground utilities, and during the night to install foundations and relocate signal cables. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible. During construction motorists and pedestrians may experience intermittent delays while crews move equipment through at-grade crossings.

 

Atherton

 

October 20 through October 26, Caltrain will be working during the day to locate underground utilities, and during the night to install foundations and relocate signal cables. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible. During construction motorists and pedestrians may experience intermittent delays while crews move equipment through at-grade crossings.

 

During work hours at the Atherton station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.

Menlo Park

 

October 20 through October 26, Caltrain will be working during the day to locate underground utilities and prune and remove trees along the project route, and during the night to locate underground utilities and install foundations. Day work hours will be 7 a.m. to 7 p.m. Night work hours will be 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

 

During work hours at the Menlo Park station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.

Palo Alto

 

October 20 through October 26, Caltrain will be working during the day to locate underground utilities and prune and remove trees along the project route, and during the night to locate underground utilities. Day work hours will be 7 a.m. to 7 p.m. Night work hours will be 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

 

During work hours at the Palo Alto station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.

Mountain View

 

October 20 through October 26, Caltrain will be working during the day to locate underground utilities and prune and remove trees along the project route, and during the night to locate underground utilities. Day work hours will be 7 a.m. to 7 p.m. Night work hours will be 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

 

During work hours at the Mountain View station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.

Sunnyvale

 

October 20 through October 26, Caltrain will be working during the day to locate underground utilities and prune and remove trees along the project route, and during the night to locate underground utilities and install foundations. Day work hours will be 7 a.m. to 7 p.m. Night work hours will be 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

 

During work hours at the Sunnyvale station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.

Santa Clara

 

October 20 through October 26, Caltrain will be working during the day to install conduit and locate underground utilities, and at night to locate underground utilities and relocate signal cables. Day work hours will be 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

 

During work hours at the Santa Clara station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call the project hotline at 650-399-9659 or toll-free at 855-463-4373.

San Jose

 

October 20 through October 26, Caltrain will be working during the day to install conduit, locate underground utilities and install a ductbank and manholes at the Traction Power Substation facility, and at night to locate underground utilities and relocate signal cables. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

 

During work hours at the San Jose stations, all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.

 

For more information, please call the dedicated outreach line at 650.508.6499; visit the website at www.calmod.org or email calmod@caltrain.com.

 

back to top

MAINTENANCE

 

Caltrain will perform routine maintenance at several locations next week. To avoid disruptions to service, the work will mainly take place Saturday through Friday from 8 p.m. to 6 a.m. For more information about this type of work, click here, or call 650.508.7726.

San Francisco to San Jose

 

Saturday, October 20, to Friday, October 26, crews will pressure wash and perform janitorial work at Caltrain stations between the San Francisco and Tamien stations.

Saturday, October 20, to Friday, October 26, crews will weld and grind rail at various locations between the San Francisco and Tamien stations. The welding crew uses air compressors, gas-powered generators, small power tools, electric-arc welders and propane heaters. Neighbors may experience maintenance noise during this time. Crews will work as quietly as possible.

San Francisco to Brisbane

 

Saturday, October 20, to Friday, October 26, crews will resurface rail between the San Francisco and Brisbane stations. Caltrain uses several different on-track, self-propelled machines to replace resurface rail, and neighbors may experience maintenance noise during this time. Crews will work as quietly as possible.

 

Menlo Park to Palo Alto

Saturday, October 20, to Friday, October 26, crews will resurface rail between the Menlo Park and Palo Alto stations. Caltrain uses several different on-track, self-propelled machines to resurface rail, and neighbors may experience maintenance noise during this time. Crews will work as quietly as possible.

Mountain View to Santa Clara

 

Saturday, October 20, to Friday, October 26, crews will resurface rail between the Mountain View and Santa Clara stations. Caltrain uses several different on-track, self-propelled machines to resurface rail, and neighbors may experience maintenance noise during this time. Crews will work as quietly as possible.

Santa Clara to San Jose

 

Saturday, October 20, to Friday, October 26, crews will change ties between the Lawrence and Tamien stations. Caltrain uses several different on-track, self-propelled machines to replace cross ties, and neighbors may experience maintenance noise during this time. Crews will work as quietly as possible.