25th Avenue Grade Separation Project

Night Work Status as of March 16, 2018

Below offers a quick glance regarding the status of the night work. For a more detailed description of these activities and their anticipated timeline, read the Night Work Overview (PDF)

Shoring 

Borel Creek    100% complete
28th Avenue    100% complete
Ped Underpass   100% complete
31st Avenue   100% complete
25th Avenue   100% complete


Pile Construction & Installation

Borel Creek   100% complete 
28th Avenue   100% complete
Ped Underpass   100% complete 
31st Avenue    100% complete
25th Avenue   100% complete

 
Additional phases of night work will be posted closer to the start of those activities.