Sign Up For Weekly Construction Updates

Construction Activity Updates

Construction activities will begin in Segment 2 and Segment 4.  Crews will begin at the northern end of those segments and proceed south, with South San Francisco and San Bruno being the first cities to see activities occur.

The anticipated activities at this time include locating underground utilities, testing soil conditions, inspecting signal/communication equipment, and tree trimming/removal. After tree trimming/removal is complete,crews will begin work on the foundations for the overhead contact system. Work will take place during the day and at night with night work occurring between 8p.m. and 6 a.m.

Upcoming Community Meetings

There is a meeting scheduled on November 28 to discuss upcoming work in San Jose.

Meeting Details:

Tuesday, November 28, 6:00-7:00 p.m.
Dr. Martin Luther King Jr. Library, Room 225
150 E San Fernando St.
San Jose, CA 95112

Weekly Construction Activity Updates

For the upcoming week, the activities associated with the electrification infrastructure component of the Caltrain Modernization Program are the following:

San Francisco 
No work anticipated. 

Brisbane
No work anticipated. 

South San Francisco
November 18 through November 22, Caltrain will be doing work during the day and night to relocate signal cables and to install OCS foundation. Foundation work activities will include excavation, drilling, placement of foundations and pouring of concrete. Day work hours will be from 7 a.m. to 5 p.m. Night work hours for November 18 will be from 7:45 p.m. to 7:45 a.m. and night work hours for November 19 through November 20 will be from 7:45 p.m. to 5:30 a.m. During construction motorists and pedestrians may experience intermittent delays while crews move equipment through at-grade crossings. We apologize for any inconvenience this may cause and the field team will work as quietly as possible. 

Parking spaces #46 to 74 at the South San Francisco Station will be blocked off to accommodate staging of material and equipment for the construction of the Peninsula Corridor Electrification Project. No Parking signage will be placed in the designated area that will be closed off to traffic.

During night work hours at the South San Francisco station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call the project hotline at 650-399-9659 or toll-free at 855-463-4373. 

San Bruno
November 18 through November 22, Caltrain will be doing work during the day and night to relocate signal cables and to install OCS foundation. Foundation work activities will include excavation, drilling, placement of foundations and pouring of concrete. Day work hours will be from 7 a.m. to 5 p.m. Night work hours for November 18 will be from 7:45 p.m. to 7:45 a.m. and night work hours for November 19 through November 20 will be from 7:45 p.m. to 5:30 a.m. During construction motorists and pedestrians may experience intermittent delays while crews move equipment through at-grade crossings. We apologize for any inconvenience this may cause and the field team will work as quietly as possible. 

During night work hours at the San Bruno station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call the project hotline at 650-399-9659 or toll-free at 855-463-4373. 

Millbrae
November 18 through November 22, Caltrain will be doing work during the day and night to locate underground utilities and remove project materials and to relocate signal cables. Day work hours will be from 7 a.m. to 5 p.m. Night work hours for November 18 will be from 7 p.m. to 7:45 a.m. and night work hours for November 20 through November 21 will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

During night work hours at the Millbrae station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call the project hotline at 650-399-9659 or toll-free at 855-463-4373. 

Burlingame
November 18 through November 22, Caltrain will be doing work during the day and night to locate underground utilities and remove project materials and to relocate signal cables. Day work hours will be from 7 a.m. to 5 p.m. Night work hours for November 18 will be from 7 p.m. to 7:45 a.m. and night work hours for November 20 through November 21 will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

During night work hours at the Burlingame station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call the project hotline at 650-399-9659 or toll-free at 855-463-4373. 

San Mateo
No work anticipated. 

Belmont
No work anticipated.

San Carlos
November 18 through November 22, Caltrain will be doing work during the day to prune and remove trees along the project route. Work hours will be from 7 a.m. and 5 p.m. We apologize for any inconvenience this may cause.

Redwood City
November 18 through November 22, Caltrain will be doing work during the day to prune and remove trees along the project route. Work hours will be from 7 a.m. and 5 p.m. We apologize for any inconvenience this may cause.


Unincorporated San Mateo County

November 18 through November 22, Caltrain will be doing work during the day to prune and remove trees along the project route. Work hours will be from 7 a.m. and 5 p.m. We apologize for any inconvenience this may cause.

Atherton
No work anticipated. 

Menlo Park
No work anticipated. 

Palo Alto
No work anticipated.

Mountain View
No work anticipated.

Sunnyvale
Not work anticipated. 

Santa Clara
No work anticipated. 

San Jose
No work anticipated.

 

For more information

Email: calmod@caltrain.com
Call: 650.399.9659 or toll free 800.279.1455
Tweet: @Caltrain

Documents

Presentations

Redwood City Work Area Community Meeting - November 2017


Belmont and San Carlos Work Area Community Meeting - October 2017


San Mateo Work Area Community Meeting - September 2017

Burlingame and Millbrae Work Area Community Meeting - August 2017

South San Francisco and San Bruno Work Area Community Meeting - July 2017

Fact Sheets

Redwood City Construction Fact Sheet - November 2017

Belmont and San Carlos Construction Fact Sheet - October 2017

Burlingame and Millbrae Construction Fact Sheet - August 2017


South San Francisco and San Bruno Construction Fact Sheet - July 2017

Notices

Direct mailer to residents in Santa Clara (November 2017) 


Direct mailer to residents in Redwood City and North Fair Oaks (November 2017) 


Direct mailer to residents in work segment 4 (November 2017)
 

Direct mailer to residents in Belmont and San Carlos (October 2017)

Direct mailer to residents in work segment 2, work area 1 and 2 (August 2017)

Direct mailer to residents in San Mateo (August 2017)

Direct mailer to residents in Millbrae and Burlingame (August 2017)

Direct mailer to residents in South San Francisco and San Bruno (June 2017)

Direct mailer to residents in  work segment 2, work area 4 and 5 (June 2017)

Direct mailer to residents in work segments 1 and 3 (January 2017)

Direct mailer to residents in work segment 2 and 4 (November 2016)