California Avenue Station Platform Improvement
Factsheet
Project Lead:
Caltrain
Contractors:
To be determined by competitive bid
Project Limits:
California Avenue Caltrain Station
Construction Cost:
$13 Million
Begin Construction:
June 2007
End Construction:
December 2008
Reason for Project:
This project will improve passenger service and safety at the station,
and allow Caltrain to eliminate the “Holdout Rule” at California Avenue.
Currently trains must “hold out” beyond the station if another train is in
the station, and cannot enter the station until the first train has left.
This project will allow more than one train to enter or pass through
the station at a time, allowing for more flexibility in scheduling trains.
Scope of Work:
The center boarding platform will be demolished, and outside
boarding platforms will be constructed to meet the standards set
by the Americans with Disabilities Act. The result is that passengers
will no longer board between the tracks but from the new platforms
outside. Center track fencing will be installed, to prevent pedestrians
from crossing the tracks, and an underpass will be constructed so
passengers can cross easily from one platform to another.
|