Burlingame Station > Construction > Timeline
Construction at Burlingame Caltrain Station - Timeline
Burlingame Station Timeline as of May 2008
Construction began June 2007, and will conclude June 2008.
-
Northbound Platform – Summer 2007 through February 2008.
-
Southbound Platform Extension and Refurbishing – Winter 2008 through Spring 2008.
-
Upgrades to Broadway, North Lane, Howard Avenue, Bayswater Avenue and Morell Avenue Pedestrian Crossing – at various times throughout project—from July 2007 to June 2008.
-
Upgrades to track at and between Broadway and Burlingame station – Summer 2007 through Winter 2008.