San Bruno Streets To Be Temporarily Closed for Construction
San Bruno Streets To Be Temporarily Closed for Construction
Beginning July 13, there will be a series of temporary road closures in San Bruno to allow for the placement of steel bridge structures above the vehicle underpass. The structures are part of the San Bruno Grade Separation Project, which will elevate the train tracks above San Bruno, San Mateo and Angus avenues.
San Bruno Avenue between Huntington and San Mateo avenues
9 p.m. Friday July 13 to 6 a.m. Saturday July 14
9 p.m. Saturday July 14 to 6 a.m. Sunday July 15
San Mateo Avenue between Huntington and 1st avenues
9 p.m. Friday July 20 to 6 a.m. Saturday July 21
9 p.m. Saturday July 21 to 6 a.m. Sunday July 22
Angus Avenue between Huntington and 1st avenues
9 p.m. Friday July 27 to 6 a.m. Saturday July 28
9 p.m. Saturday July 28 to 6 a.m. Sunday July 29
Detour signs will be posted in the area to help direct traffic. All work will be done in accordance with Caltrain and city agreements and ordinances.
The $147 million grade separation project includes a new elevated train station between San Bruno and San Mateo avenues will replace the existing station. The project also includes three pedestrian underpasses, one near Sylvan Avenue, one at the new station and another between Euclid Avenue and Walnut Street.
Questions can be addressed to the Caltrain Office of Public Affairs, 650.508.7726 or sbgradesep@caltrain.com.
###