Caltrain Rail Grinding Will Result in Quieter Trains
Caltrain Rail Grinding Will Result in Quieter Trains
Caltrain will begin a three-week rail grinding project March 18 that will result in measurably reduced noise impacts for neighbors next to the right of way and a safer, smoother ride for passengers. A rail-mounted, industrial-sized grinder will be used to smooth out defects and restore the shape of the rail.
During the rail maintenance, there will be noise impacts to areas immediately adjacent to the rail alignment while the grinding is taking place. The contractor is required to maintain noise levels below 85 decibels at a distance of 25 feet from the center of the rail. This noise level roughly compares to shop tools or someone shouting but is quieter than a train whistle or a gas-powered lawn mower.
The equipment must be used when there is reduced train traffic, which means the grinding must take place from 10 p.m. to 4:30 a.m. The work will begin in Redwood City and proceed on the northbound track reaching San Francisco about March 23. The equipment will then travel back to San Jose on the southbound tracks. Finally, the equipment will complete the work from San Jose to Redwood City. Work at any one location will be completed in one to two nights. The entire project will be completed by April 13.
Editors Note:
Here is a tentative schedule of work locations:
Northbound Tracks:
| Scheduled Date | Stations |
| Wednesday, March 18 | Redwood City to Hillsdale |
| Thursday, March 19 | Hillsdale to Burlingame |
| Friday, March 20 | Burlingame to San Bruno |
| Saturday, March 21 | San Bruno to Bayshore |
| Sunday, March 22 | Bayshore to South San Francisco |
| Monday, March 23 | San Francisco |
| Wednesday, April 8 | San Jose to Santa Clara |
| Thursday, April 9 | Santa Clara to Sunnyvale |
| Friday, April 10 | Sunnyvale to San Antonio |
| Saturday, April 11 | San Antonio to Palo Alto |
| Sunday, April 12 | Palo Alto to Redwood City |
| Monday, April 13 | Redwood City |
Southbound Tracks:
| Scheduled Date | Stations |
| Wednesday, March 25 | San Francisco |
| Thursday, March 26 | San Francisco to Bayshore |
| Friday, March 27 | Bayshore to South San Francisco |
| Saturday, March 28 | South San Francisco to Millbrae |
| Sunday, March 29 | Millbrae to Hayward Park |
| Monday, March 30 | Hayward Park to San Carlos |
| Wednesday, April 1 | San Carlos to Atherton |
| Thursday, April 2 | Atherton to California Avenue |
| Friday, April 3 | California Avenue to Mountain View |
| Saturday, April 4 | Mountain View to Lawrence |
| Sunday, April 5 | Lawrence to Santa Clara |
| Monday, April 6 | Santa Clara to San Jose Tamien |
03/11/2009 - tcb
Media Contact: Tasha Bartholomew, 650.508.7927