Caltrain Rail Grinding Will Result in Quieter Trains

Caltrain Rail Grinding Will Result in Quieter Trains

Caltrain will begin a three-week rail grinding project March 18 that will result in measurably reduced noise impacts for neighbors next to the right of way and a safer, smoother ride for passengers. A rail-mounted, industrial-sized grinder will be used to smooth out defects and restore the shape of the rail.

During the rail maintenance, there will be noise impacts to areas immediately adjacent to the rail alignment while the grinding is taking place. The contractor is required to maintain noise levels below 85 decibels at a distance of 25 feet from the center of the rail. This noise level roughly compares to shop tools or someone shouting but is quieter than a train whistle or a gas-powered lawn mower.

The equipment must be used when there is reduced train traffic, which means the grinding must take place from 10 p.m. to 4:30 a.m. The work will begin in Redwood City and proceed on the northbound track reaching San Francisco about March 23. The equipment will then travel back to San Jose on the southbound tracks. Finally, the equipment will complete the work from San Jose to Redwood City. Work at any one location will be completed in one to two nights. The entire project will be completed by April 13.

Editors Note:
Here is a tentative schedule of work locations:

Northbound Tracks:

Scheduled Date Stations
Wednesday, March 18  Redwood City to Hillsdale
Thursday, March 19 Hillsdale to Burlingame 
Friday, March 20 Burlingame to San Bruno
Saturday, March 21 San Bruno to Bayshore
Sunday, March 22 Bayshore to South San Francisco
Monday, March 23 San Francisco
Wednesday, April 8 San Jose to Santa Clara
Thursday, April 9 Santa Clara to Sunnyvale
Friday, April 10 Sunnyvale to San Antonio
Saturday, April 11 San Antonio to Palo Alto
Sunday, April 12 Palo Alto to Redwood City
Monday, April 13 Redwood City


Southbound Tracks:

Scheduled Date Stations
Wednesday, March 25 San Francisco
Thursday, March 26 San Francisco to Bayshore
Friday, March 27 Bayshore to South San Francisco
Saturday, March 28 South San Francisco to Millbrae
Sunday, March 29 Millbrae to Hayward Park
Monday, March 30 Hayward Park to San Carlos
Wednesday, April 1 San Carlos to Atherton
Thursday, April 2 Atherton to California Avenue
Friday, April 3 California Avenue to Mountain View
Saturday, April 4 Mountain View to Lawrence
Sunday, April 5 Lawrence to Santa Clara
Monday, April 6 Santa Clara to San Jose Tamien
03/11/2009 - tcb
Media Contact: Tasha Bartholomew, 650.508.7927