Caltrain Construction and Maintenance: June 9 to June 15, 2012

Caltrain Construction and Maintenance: June 9 to June 15, 2012

Construction

San Bruno Grade Separation Project

Pile driving, which is an essential step in the construction of the foundation of the grade separation, began in February. Pre-drilling holes in preparation for the resumption of pile driving will continue this week. The drilling will be limited to weekday daytime hours from 9 a.m. to 3 p.m. The work will involve excavation and drilling into the ground.

Other work, which includes digging with a backhoe and mini-excavator, will be done from 7 a.m. to

4 p.m. Crews will excavate, install temporary shoring, install culverts, install utility infrastructure, prepare foundations, install rebar and pour concrete. Crews will use medium and heavy duty diesel vehicles to transport dirt and concrete.

Night work will occur from Sunday, June 10, through Friday, June 15, between 11 p.m. and 7 a.m. Crews will excavate and install temporary shoring in preparation for pouring foundations and building retaining walls.

The $147 million project will elevate the Caltrain tracks above three existing at-grade street crossings at San Bruno, San Mateo and Angus avenues. A new elevated Caltrain station between San Bruno and San Mateo a0venues will replace the station at Sylvan Avenue.

For more information, please call the dedicated outreach line at 650.508.7726 or email sbgradesep@caltrain.com.

Maintenance

Caltrain will perform routine maintenance at several locations next week. To avoid delays to passengers, the work will take place Sunday through Friday from 8 p.m. to 6 a.m. There will be some construction noise but crews will work as quietly as possible. For more information about this type of work, click here.

South San Francisco to Millbrae
Sunday, June 10, through Friday, June 15, crews will excavate, grade, and install retaining walls along the tracks between the South San Francisco and Millbrae stations.

Hillsdale to Atherton
Sunday, June 10, through Thursday, June 14, crews will operate light on-track machinery to grind and align tracks between the Hillsdale and Atherton stations.

Santa Clara to San Jose
Sunday, June 10, through Thursday, June 14, crews will weld tracks, grind tracks and operate medium duty on-track machinery to remove and replace ties between the Santa Clara and Tamien stations.

San Francisco
Monday, June 11, through Friday, June 15, crews will operate hand tools and table saws to upgrade the public announcement system at the San Francisco station.

###

Media Contact: Tasha Bartholomew, 650.508.7927