Caltrain Construction and Maintenance: June 30 to July 6, 2012
Caltrain Construction and Maintenance: June 30 to July 6, 2012
Construction
San Bruno Grade Separation Project
Pile driving, which is an essential step in the construction of the foundation of the grade separation, began in February. Pre-drilling holes in preparation for the resumption of pile driving will continue this week. Pile driving is scheduled to continue this week, with the exception of the Fourth of July. The drilling and pile driving will be limited to weekday daytime hours from 9 a.m. to 3 p.m. The work will involve excavation, drilling and machines that hammer or drive columns into the ground. A total of 100 piles will be driven into the ground over the course of two weeks. At times, noise levels could be as high as 75 decibels, and we apologize for any inconvenience this may cause.
Other work, which includes digging with a backhoe and mini-excavator, will be done in the daytime from 7 a.m. to 4 p.m. Crews will excavate, install temporary shoring, demolish concrete, install utility infrastructure, prepare foundations, install rebar and pour concrete. Crews will use medium and heavy duty diesel vehicles to transport dirt and concrete.
Night work will occur from Sunday, July 1, through Friday, July 6, between 11 p.m. and 7 a.m. Crews will excavate and install temporary shoring in preparation for pouring foundations and building retaining walls.
The $147 million project will elevate the Caltrain tracks above three existing at-grade street crossings at San Bruno, San Mateo and Angus avenues. A new elevated Caltrain station between San Bruno and San Mateo avenues will replace the station at Sylvan Avenue.
For more information, please call the dedicated outreach line at 650.508.7726 or email sbgradesep@caltrain.com.
Maintenance
Caltrain will perform routine maintenance at several locations next week. To avoid delays to passengers, the work will take place Sunday through Friday from 8 p.m. to 6 a.m. There will be some construction noise but crews will work as quietly as possible. For more information about this type of work, click here.
San Francisco
Monday, July 2, through Friday, July 6, crews will test highway grade crossings between the San Francisco and Bayshore stations. Monday, July 2, Tuesday, July 3, Thursday, July 5, and Friday, July 6, crews will perform work to upgrade the public announcement system at the San Francisco station. Monday, July 2, through Wednesday, July 4, crews will weld and grind tracks at the San Francisco station.
Brisbane to Redwood City
Sunday, July 1, through Thursday, June 28, crews will test highway grade crossings, switches and signals between the Bayshore and Redwood City stations.
San Mateo
Friday, July 6, crews will install a pedestrian gate and vehicle gate on the east side of the right of way between the Hayward Park and Hillsdale stations.
Belmont to Atherton
Sunday, July 1, through Wednesday, July 4, crews will resurface tracks between the Belmont and Atherton stations.
Monday, July 2, Tuesday, July 3, Thursday, July 5, and Friday, July 6, crews will install fencing just north of the Belmont station near the west side parking lot.
Redwood City to San Jose
Saturday, June 30, through Friday, July 6, crews will test switches and signals between the Redwood City and College Park stations.
Saturday, June 30, through Friday, July 6, crews will test highway grade crossings between the Redwood City and Capitol stations.
Tuesday, July 3, and Wednesday July 4, crews will resurface tracks between the Redwood City and Sunnyvale stations.
Monday, July 2, through Friday, July 6, crews will test switches and signals between the Santa Clara and Capitol stations.
San Jose
Sunday, July 1, through Tuesday, July 3, and again on Thursday, July 5, crews will replace cross ties between the College Park and San Jose stations. Sunday, July 1, crews will weld and grind tracks between the Sam Jose and Tamien stations.
###
Media Contact: Tasha Bartholomew, 650.508.7927