Caltrain Construction and Maintenance: June 23 to June 29, 2012

Caltrain Construction and Maintenance: June 23 to June 29, 2012

Construction

San Bruno Grade Separation Project

Pile driving, which is an essential step in the construction of the foundation of the grade separation, began in February. Pre-drilling holes in preparation for the resumption of pile driving will continue this week. Pile driving is scheduled to continue on Thursday, June 28. The drilling and pile driving will be limited to weekday daytime hours from 9 a.m. to 3 p.m. The work will involve excavation, drilling and machines that hammer or drive columns into the ground. A total of 100 piles will be driven into the ground over the course of two weeks. At times, noise levels could be as high as 75 decibels, and we apologize for any inconvenience this may cause.

Other work, which includes digging with a backhoe and mini-excavator, will be done in the daytime from 7 a.m. to 4 p.m. Crews will excavate, install temporary shoring, demolish concrete, install utility infrastructure, prepare foundations, install rebar and pour concrete. Crews will use medium and heavy duty diesel vehicles to transport dirt and concrete.

Night work will occur from Sunday, June 24, through Friday, June 29, between 11 p.m. and 7 a.m. Crews will excavate and install temporary shoring in preparation for pouring foundations and building retaining walls.

The $147 million project will elevate the Caltrain tracks above three existing at-grade street crossings at San Bruno, San Mateo and Angus avenues. A new elevated Caltrain station between San Bruno and San Mateo avenues will replace the station at Sylvan Avenue.

For more information, please call the dedicated outreach line at 650.508.7726 or email sbgradesep@caltrain.com.

Maintenance

Caltrain will perform routine maintenance at several locations next week. To avoid delays to passengers, the work will take place Sunday through Friday from 8 p.m. to 6 a.m. There will be some construction noise but crews will work as quietly as possible. For more information about this type of work, click here.

San Francisco
Monday, June 25, through Friday, June 29, crews will test highway grade crossings between the San Francisco and Bayshore stations. Monday, June 25, through Friday, June 29, crews will perform work to upgrade the public announcement system at the San Francisco station.

South San Francisco to Millbrae
Sunday, June 24, through Friday, June 29, crews will excavate, grade, and set wall panels between the South San Francisco and Millbrae stations.

San Francisco to Redwood City
Monday, June 25, through Thursday, June 28, crews will test highway grade crossings between the San Francisco and Redwood City stations.

San Francisco to San Jose
Saturday, June 23, and Sunday, June 24, crews will operate a special train between San Francisco and Tamien stations in order to inspect the track for defects.

San Mateo to Belmont
Sunday, June 24, crews will operate medium duty on-track machinery to remove and replace ties between the San Mateo and Belmont stations.

Hillsdale to Atherton
Sunday, June 24, through Thursday, June 28, crews will operate light on-track machinery to grind and align tracks between the Hillsdale and Atherton stations.

San Carlos to San Jose
Saturday, June 23, through Friday, June 29, crews will test highway grade crossings between the San Carlos and Tamien stations.

Santa Clara to San Jose
Sunday, June 24, through Thursday, June 28, crews will weld and grind tracks, and operate medium duty on-track machinery to remove and replace ties between the Santa Clara and Tamien stations.

###

Media Contact: Tasha Bartholomew, 650.508.7927