Caltrain Construction and Maintenance: June 16 to June 22, 2012

Caltrain Construction and Maintenance: June 16 to June 22, 2012

Construction

San Bruno Grade Separation Project

Pile driving, which is an essential step in the construction of the foundation of the grade separation, began in February. Pre-drilling holes in preparation for the resumption of pile driving will continue this week. Pile driving is scheduled to resume on Thursday, June 21. The drilling and pile driving will be limited to weekday daytime hours from 9 a.m. to 3 p.m. The work will involve excavation, drilling and machines that hammer or drive columns into the ground. A total of 100 piles will be driven into the ground over the course of two weeks. At times, noise levels could be as high as 75 decibels, and we apologize for any inconvenience this may cause.

On Saturday, June 16, 1st Street will be permanently closed at San Mateo Avenue in order to improve traffic safety. Other work, which includes digging with a backhoe and mini-excavator, will be done from 7 a.m. to 4 p.m. Crews will excavate, install temporary shoring, demolish concrete, install utility infrastructure, prepare foundations, install rebar and pour concrete. Crews will use medium and heavy duty diesel vehicles to transport dirt and concrete.

Night work will occur from Sunday, June 17, through Friday, June 22, between 11 p.m. and 7 a.m. Crews will install utilities, excavate and install temporary shoring in preparation for pouring foundations and building retaining walls.

The $147 million project will elevate the Caltrain tracks above three existing at-grade street crossings at San Bruno, San Mateo and Angus Avenues. A new elevated Caltrain station between San Bruno and San Mateo Avenues will replace the station at Sylvan Avenue.

For more information, please call the dedicated outreach line at 650.508.7726 or email sbgradesep@caltrain.com.

Maintenance

Caltrain will perform routine maintenance at several locations next week. To avoid delays to passengers, the work will take place Sunday through Friday from 8 p.m. to 6 a.m. There will be some construction noise but crews will work as quietly as possible. For more information about this type of work, click here.

San Francisco
Monday, June 18, through Friday, June 22, crews will operate hand tools and table saws to upgrade the public announcement system at the San Francisco station.

San Francisco to Tamien
Monday, June 18, through Friday, June 22, crews will operate a special train between San Francisco and Tamien stations in order to inspect the track for defects. Wednesday, June 20, through Friday, June 22, crews will perform surveys on Caltrain tunnels.

South San Francisco to Millbrae
Saturday, June 16, through Friday, June 22, crews will excavate, grade and set concrete panels between the South San Francisco and Millbrae stations.

San Mateo to Belmont
Monday, June 18, through Thursday, June 21, crews will operate medium duty on-track machinery to remove and replace ties between the San Mateo and Belmont stations.

Hillsdale to Atherton
Sunday, June 17, through Thursday, June 21, crews will operate light on-track machinery to grind and align tracks between the Hillsdale and Atherton stations.

Santa Clara to San Jose
Sunday, June 17, crews will weld, grind tracks and operate medium duty on-track machinery to remove and replace ties between the Santa Clara and Tamien stations.

###