Caltrain Construction and Maintenance: Aug. 18 to Aug. 24, 2012

Caltrain Construction and Maintenance: Aug. 18 to Aug. 24, 2012

Construction

 

San Bruno Grade Separation Project

Pile driving is scheduled to continue this week. Pile driving will be limited to weekday daytime hours from 9 a.m. to 3 p.m. The work will involve excavation, drilling and machines that hammer or drive columns into the ground. A total of 100 piles will be driven into the ground over the course of three weeks. This will be the final week of pile driving. At times, noise levels could be as high as 75 decibels, and we apologize for any inconvenience this may cause.

Other work, which includes digging with a backhoe and mini-excavator, will be done in the daytime from 7 a.m. to 4 p.m. Crews will excavate, grade, install utility infrastructure, demolish concrete, install shoring, place concrete panels using a crane, install steel girders, and pour concrete. Crews will use medium and heavy duty diesel vehicles to transport dirt and concrete.

Night work will occur from Sunday, Aug. 19, through Friday, Aug.24, between 11 p.m. and 7 a.m. Crews will operate machinery to vibrate steel supports from the ground.

The $147 million project will elevate the Caltrain tracks above three existing at-grade street crossings at San Bruno, San Mateo and Angus avenues. A new elevated Caltrain station between San Bruno and San Mateo avenues will replace the station at Sylvan Avenue.

For more information, please call the dedicated outreach line at 650.508.7726 or email sbgradesep@caltrain.com.

 

Maintenance

Caltrain will perform routine maintenance at several locations next week. To avoid delays to passengers, the work will take place Saturday through Friday from 8 p.m. to 6 a.m. There will be some construction noise but crews will work as quietly as possible. For more information about this type of work, click here.

 

San Francisco to San Jose
Saturday, Aug. 18, through Friday, Aug. 24, crews will power wash and perform janitorial work at Caltrain stations between the San Francisco and Tamien stations.

 

San Francisco to South San Francisco
Sunday, Aug. 19, through Thursday, Aug. 23, crews will weld and grind tracks between the San Francisco and South San Francisco stations.

 

Palo Alto to Sunnyvale
Sunday, Aug. 19, crews will operate medium duty on-track machinery to grind and align tracks between the California Avenue and Lawrence stations.

Mountain View
Sunday, Aug. 19, through Thursday, Aug. 23, crews will grind and level uneven asphalt at the crossing between the San Antonio and Mountain View stations.

Sunnyvale to Santa Clara
Sunday, Aug. 19, through Thursday, Aug. 23, crews will operate medium duty on-track machinery to remove and replace ties between the Lawrence and Santa Clara stations.

 

Mountain View to Sunnyvale
Monday, Aug. 20, through Thursday, Aug. 23, crews will operate medium duty on-track machinery to grind and align tracks between the Mountain View and Lawrence stations.

 

###




 

Contact: Tasha Bartholomew, 650.508.7927