Caltrain Construction and Maintenance: April 14 to 20, 2012
Caltrain Construction and Maintenance: April 14 to 20, 2012
Construction
San Bruno Grade Separation Project
Pile driving, which is the first step in the construction of the foundation of the grade separation, began in February. Pile driving is on hold this week. A total of 361 piles will be driven into the ground over the course of six to eight weeks. More than 320 piles have been driven to date.
Other work, which includes digging with a backhoe and mini-excavator will be done from 7 a.m. to 4 p.m. Hydroseeding and sandblasting of concrete will occur, and temporary shoring will be installed in preparation for concrete pouring. Crews will prepare foundations and pour concrete.
Night work will occur from Sunday, April 15, through Friday, April 20, between 11 p.m. and 7 a.m. Crews will excavate and grade in order to prepare for construction of retaining walls. Temporary shoring will be installed in preparation for building the retaining walls.
The $147 million project will elevate the Caltrain tracks above three existing at-grade street crossings at San Bruno, San Mateo and Angus Avenues. A new elevated Caltrain station between San Bruno and San Mateo Avenues will replace the station at Sylvan Avenue.
For more information, please call the dedicated outreach line at 650.508.7726 or email sbgradesep@caltrain.com.
Maintenance
Caltrain will perform routine maintenance at several locations next week. To avoid delays to passengers, the work will take place Sunday through Thursday from 8 p.m. to 6 a.m. There will be some construction noise but crews will work as quietly as possible. For more information about this type of work, click here.
San Francisco to Menlo Park
Saturday, April 14, through Friday, April 20, crews will be surveying signal houses between the San Francisco and Menlo Park stations.
San Francisco
Sunday, April 15, through Thursday, April 19, crews will weld and grind tracks between the San Francisco and 22nd Street stations.
San Francisco to South San Francisco
Sunday, April 15, through Thursday, April 19, crews will operate light on-track machinery to grind and align tracks between the San Francisco and South San Francisco stations.
South San Francisco to Millbrae
Sunday, April 15, through Friday, April 20, crews will excavate, install utilities, grade, and load aggregate material between the South San Francisco and Millbrae stations.
###
Media Contact: Christine Dunn, 650.508.6238